120 metre Steel Truss Bridge Cantilever Over Arun River Nepal

2024/4/13      view:
120 metre Steel Truss Bridge Cantilever Over Arun River Nepal

This bridge over the Arun River provides all season access for 203,000 people and helps, in conjunction with the other projects in the district, to lift them out of poverty and reduce their reliance on aid in both the immediate district and the six other districts directly served by the new crossing.

The Arun River is both fast flowing and full throughout the year, so a cantilever launch method for the erection of the steel truss was chosen.

This required detailed consideration of the erection system to be built into the design and the bridge was cantilevered from both sides of the river with incremental erection of the truss facilitated by lifting the individual steel sections with gantry cranes supplied as part of the ZHM steelwork.

Local residents were hired where possible, and made a valuable contribution to the project.

The construction was carried out by local contractor  

The bridge was opened to traffic in October 2013 with official inauguration in January 2014.


120_metre_Steel_Truss_Bridge_Cantilever_Over_Arun_River_Nepal_01

Steel Structure in usage after installation completion of 120 metre Steel Truss Bridge Cantilever Over Arun River Nepal

120_metre_Steel_Truss_Bridge_Cantilever_Over_Arun_River_Nepal_02

Steel Structure in installation of 120 metre Steel Truss Bridge Cantilever Over Arun River Nepal

120_metre_Steel_Truss_Bridge_Cantilever_Over_Arun_River_Nepal_03

Steel Structure in installation of 120 metre Steel Truss Bridge Cantilever Over Arun River Nepal

120_metre_Steel_Truss_Bridge_Cantilever_Over_Arun_River_Nepal_04

Steel Structure in usage after installation completion of 120 metre Steel Truss Bridge Cantilever Over Arun River Nepal

120_metre_Steel_Truss_Bridge_Cantilever_Over_Arun_River_Nepal_05


120_metre_Steel_Truss_Bridge_Cantilever_Over_Arun_River_Nepal_06

Steel Structure in installation of 120 metre Steel Truss Bridge Cantilever Over Arun River Nepal

120_metre_Steel_Truss_Bridge_Cantilever_Over_Arun_River_Nepal_07

Steel Structure in production of 120 metre Steel Truss Bridge Cantilever Over Arun River Nepal

120_metre_Steel_Truss_Bridge_Cantilever_Over_Arun_River_Nepal_08

Steel Structure container loading for ocean shipment for the 120 metre Steel Truss Bridge Cantilever Over Arun River Nepal